Sky Studios New Studios: a £2.2m Daikin VRV IV installation across 7 office spaces over 3 floors, won on tender.

As part of its New Studios development, Sky Studios needed a complete heating and cooling solution for seven new build office spaces spread across three floors. Going up against the market on a competitive tender, Zircon Building Services secured the project on technical strength and price — and delivered the full Daikin VRV IV heat recovery installation on time and on budget.

ClientSky Studios
Project typeNew build — New Studios development
Scope7 office spaces · 3 floors
SystemDaikin VRV IV Heat Recovery
Contract value£2.2m
Awarded viaCompetitive tender
£2.2m
Contract value, won via competitive tender
7
Office spaces, each individually climate-controlled
3
Floors covered — one coordinated VRV IV platform
0
Days lost to programme — on time, on budget

Seven new offices, three floors, one coordinated climate solution.

As part of its New Studios development, Sky Studios was bringing forward seven brand new office spaces spread over three floors to house the teams supporting the wider production facility. The brief to the market was clear: deliver a high-performance heating and cooling solution that would tie all seven offices together on a single, well-engineered platform — flexible enough to handle differing loads floor by floor and room by room, and robust enough for long-term commercial use.

The project was put out to competitive tender, with bidders judged on technical approach, programme certainty and commercial value. Zircon Building Services was successful, securing the £2.2m contract to design, install and commission the air conditioning system across all seven offices.

What the client needed

  • Complete HVAC solution for 7 office spaces over 3 floors
  • Independent control in every office, every floor
  • Quiet, discreet indoor units suited to working office environments
  • A single Daikin VRV platform — simple to operate, easy to maintain
  • Programme certainty against a fixed New Studios handover date

Daikin VRV IV heat recovery, designed and installed by Zircon.

Zircon specified a Daikin VRV IV heat recovery (3-pipe) platform — the ideal fit for a multi-floor office estate where one space may be calling for cooling while the office next door, or the floor above, needs heat. Energy that would otherwise be rejected outside is moved between zones, which is both more efficient and more comfortable for the people using the building.

Why Daikin VRV IV heat recovery?

VRV IV combines variable refrigerant flow with Daikin's VRT smart control, so the system continuously self-tunes to the real load in each space. Indoor units across all seven offices and three floors operate independently — staff set their own temperature in their own room without affecting anyone else.

For a new build of this profile, VRV IV gives the client modern, low-noise comfort cooling and heating from a single, well-supported platform with a long, predictable service life.

Manufacturer
Daikin
Platform
VRV IV / IV+
Configuration
Heat recovery (3-pipe)
Coverage
7 offices · 3 floors
Control
VRT smart control, individual zone setpoints
Installer
Zircon Building Services

Engineered at design stage, delivered floor by floor to programme.

Working alongside the principal contractor and design team from early in the New Studios programme, Zircon's engineers carried out heat-load calculations office-by-office and floor-by-floor, sized the VRV system to match real demand and coordinated services routes with the wider M&E package — keeping the system properly engineered, not over-specified.

On site, our installation team handled the full scope across all three floors: indoor units positioned for comfort and acoustics in each office, refrigerant pipework, condensate drainage, electrical first and second fix, controls integration, commissioning and a clean handover into the client's facilities team.

Delivered by Zircon

  • Tender win — technical proposal & commercial submission
  • Design coordination across the new build M&E package
  • Daikin VRV IV heat recovery supply and installation
  • Indoor unit selection, positioning and acoustic consideration
  • Refrigerant pipework, condensate, electrical first & second fix
  • Commissioning, controls set-up and client handover

Precision climate control across every zone — on time and on budget.

01

Precision across 7 offices, 3 floors

Every office runs to its own setpoint on every floor. Heating and cooling can happen at the same time across the building, so each space gets exactly the conditions its occupants need without compromising on energy use.

02

On time, on budget

The full £2.2m installation was delivered to the agreed programme and within the agreed cost — a key requirement on a new build with a fixed handover date and a busy wider construction programme.

03

One platform, simple to run

A single Daikin VRV IV system ties all seven offices together — easier for the in-house team to operate, monitor and maintain over the long term than a patchwork of standalone units.

Planning a similar project?

Zircon Building Services designs, installs and maintains commercial air conditioning, heating and M&E systems across the UK.

Talk to our team